Consider this information about an activity: es = 12, ef = 18, ls = 14, lf = 20. what is the amount of slack associated with this activity?

+4
Answers (1)
  1. 23 May, 09:26
    0
    The slack can easily be explained as the difference between latest start (ls) and earliest start (es) of an activity. As the above example, we can easily now calculate slack as the follow: slack = LS - ES or LF - EF So, the correct answer will be LS - ES = 14 - 12 = 2 or LF - EF = 20-18 = 2 So, the slack associated with this activity is 2.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Consider this information about an activity: es = 12, ef = 18, ls = 14, lf = 20. what is the amount of slack associated with this activity? ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.