A non bottleneck worker currently has an idle time of 20 seconds per unit. Because of the large demand, the company improves the process by adding more capacity to the bottleneck. How does this impact the idle time of the worker?
1. The idle time would decrease.
2. The idle time would stay the same.
3. The idle time would increase.
4. Cannot determine from the given information.
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A non bottleneck worker currently has an idle time of 20 seconds per unit. Because of the large demand, the company improves the process by ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Home » Business » A non bottleneck worker currently has an idle time of 20 seconds per unit. Because of the large demand, the company improves the process by adding more capacity to the bottleneck. How does this impact the idle time of the worker? 1.