Ask Question
11 July, 16:01

On April 1, 2014, Headland Inc. entered into a cost-plus-fixed-fee contract to construct an electric generator for Altom Corporation. At the contract date, Headland estimated that it would take 2 years to complete the project at a cost of $1,962,000. The fixed fee stipulated in the contract is $467,000. Headland appropriately accounts for this contract under the percentage-of-completion method. During 2020, Headland incurred costs of $829,900 related to the project. The estimated cost at December 31, 2020, to complete the contract is $1,100,100. Altom was billed $566,000 under the contract.

Prepare a schedule to compute the amount of gross profit to be recognized by Headland under the contract for the year ended December 31, 2014.

+5
Answers (1)
  1. 11 July, 16:16
    0
    Gross profit to be recognized = $196,140

    Explanation:

    Headland Inc.

    Gross profit to be recognized by Headland at December 31, 2014 ending

    Estimated contract cost $1,962,000

    Fixed fee $467,000

    Total $1,962,000 + $467,000) $2,429,000

    Total estimated cost $1,962,000

    Gross profit ($2,429,000 - $1,962,000) $467,000

    percentage of completion: ($829,900/1,962,000) 42%

    Gross profit to be recognized: $467,000*42% $196,140
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “On April 1, 2014, Headland Inc. entered into a cost-plus-fixed-fee contract to construct an electric generator for Altom Corporation. At ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers