Tenderfoot company uses a job costing system. The work in process inventory on December 31, 2012 consisted of Job No. 175. This job had been charged with direct materials of $17,400 and direct labor of $20,000. Overhead is charged at a rate of 80% of direct labor cost. The cost of Job No. 175 was:

+3
Answers (1)
  1. 19 August, 08:52
    0
    Total cost = $53,400

    Explanation:

    Giving the following information:

    Job No. 175:

    This job had been charged with:

    Direct materials of $17,400

    Direct labor of $20,000.

    Overhead is charged at a rate of 80% of direct labor cost

    Total cost = direct labor + direct materials + manufacturing overhead

    Total cost = 20000 + 17400 + (0.80*20000) = $53,400
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Tenderfoot company uses a job costing system. The work in process inventory on December 31, 2012 consisted of Job No. 175. This job had ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.