Project A has an initial investment of - 255,852 and project B has an initial investment of - 63,595. What is the incremental cash flow for time zero when evaluating this project?

+3
Answers (1)
  1. 25 March, 04:52
    0
    If project A is chosen, incremental cash flow is - $192,257

    If project B is chosen, incremental cash flow is $192,257

    Explanation:

    If the company chooses project A over project B, the incremental cash flow would the amount of money expended more or less because of the choice made, hence incremental cash flow would be $-192257 (-$255,852 (-$63,595)).

    However, if project is chosen instead incremental cash flow is $192,257, in other words the company is saving $192,257 by opting for project B instead of A
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Project A has an initial investment of - 255,852 and project B has an initial investment of - 63,595. What is the incremental cash flow for ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers