Janitor Supply produces an industrial cleaning powder that requires 40 grams of material at $0.10 per gram and. 25 direct labor hours at $12.00 per hour. Overhead is applied at the rate of $18 per direct labor hour. What is the total standard cost for one unit of product that would appear on a standard cost card?

+1
Answers (1)
  1. 21 October, 13:14
    0
    Answer: $11.50

    Explanation: As we know that : -

    Total standard cost for one unit = standard material cost + standard direct labor cost + standard overhead cost

    where,

    standard material cost = (40 grams) * ($0.10) = $4

    standard direct labor cost = (0.25 hrs) * ($12) = $3

    standard overhead cost = (0.25 hrs) * ($18) = $4.5

    therefore : -

    Total standard cost for one unit = $4 + $3 + $4.5 = $11.5
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Janitor Supply produces an industrial cleaning powder that requires 40 grams of material at $0.10 per gram and. 25 direct labor hours at ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.