Extreme Builders constructs houses. The standard labor rate is $25 per hour and the standard number of hours is 15,000 hours per home. During the year, it constructed 12 homes using 18,000 labor hours per home and a rate of $28 per hour. Calculate the Extreme Builders' labor rate variance. a.$648,000 F b.$540,000 F c.$648,000 U d.$540,000 U

+4
Answers (1)
  1. 8 June, 21:20
    0
    Direct labor rate variance = $648,000 unfavorable

    Explanation:

    Giving the following information:

    The standard labor rate is $25 per hour. During the year, it constructed 12 homes using 18,000 labor hours per home and a rate of $28 per hour.

    To calculate the direct labor rate variance, we need to use the following formula:

    Direct labor rate variance = (Standard Rate - Actual Rate) * Actual Quantity

    Direct labor rate variance = (25 - 28) * 216,000

    Direct labor rate variance = $648,000 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Extreme Builders constructs houses. The standard labor rate is $25 per hour and the standard number of hours is 15,000 hours per home. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.