In 3 minutes, a conveyor belt moves 300 pounds of recyclable aluminum from the delivery truck to a storage area. A smaller belt moves the same quantity of cans the same distance in 24 minutes. If both belts are used, find how long it takes to move the cans to the storage area.

+2
Answers (1)
  1. 12 September, 07:50
    0
    You need to add their rates of working

    to get their rate working together

    For the bigger belt:

    Rate1 = (300 pounds of aluminum) / (3 minutes)

    For the smaller belt:

    Rate2 = (300 pounds of aluminum) / (7 minutes)

    I will call moving 300 pounds of aluminum 1 job

    So, Rate1 = 1/3

    and Rate2 = 1/7

    Let t = time in minutes for both belts to do this job

    Rate 1 + rate2 = Rate3

    1/3 + 1/7+1/t

    Multiply both sides by 21t

    7t+3t=21

    10t=21

    t=2.1 min

    Note that. 1 min = 6 sec

    Working togethers, the belts can move the cans

    in 2 min and 6 sec
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “In 3 minutes, a conveyor belt moves 300 pounds of recyclable aluminum from the delivery truck to a storage area. A smaller belt moves the ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.