If 5 workers can pave 10 driveways in 30 days, how many days would it take 20 workers to pave 38 driveways?

+1
Answers (1)
  1. 28 January, 14:19
    0
    Given that 5 workers can pave 10 driveways in 30 days, then:

    let x be the number of days that can take 20 workers to complete 38 drive ways;

    therefore:

    proportion of work completed by 5 workers will be:

    5*30/10

    =15

    proportion of work completed by 20 workers will be:

    20*x/38

    The time taken for 20 workers to complete 38 driveways will be:

    15=20/38x

    x=15*38/20

    x=28 1/2

    The answer is 28.5 days