The number of days needed to remodel a house varies inversely as the number of people working on the job. It takes 18 weeks for 4 people to complete the project. If the job has to be finished in 8 weeks, how many people are needed?
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The number of days needed to remodel a house varies inversely as the number of people working on the job. It takes 18 weeks for 4 people to ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.