The number of days needed to remodel a house varies inversely as the number of people working on the job. It takes 18 weeks for 4 people to complete the project. If the job has to be finished in 8 weeks, how many people are needed?

+5
Answers (1)
  1. 28 November, 15:11
    0
    To solve this problem, you must follow the proccedure below:

    1. First, you must calculate the Constant of proportionality "k".

    2. The problem says that t he number of days needed to remodel a house varies inversely as the number of people working on the job. Then:

    Number of days=K/Number of people

    K = (Number of days) (Number of people)

    18 weeks=135 days

    K=135x4

    K=540

    3. Now, you have:

    Number of days=540/Number of people

    8 weeks=60 days

    Number of people=540/60

    Number of people=9

    How many people are needed?

    The answer is: 9
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The number of days needed to remodel a house varies inversely as the number of people working on the job. It takes 18 weeks for 4 people to ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.