A person-hour is a unit of measure representing one person working for one hour. A construction foreman estimates that it will take 2880 person-hours to build a new library. If 12 workers are scheduled to work on the project at the same time how many hours will it take to complete the project?
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A person-hour is a unit of measure representing one person working for one hour. A construction foreman estimates that it will take 2880 ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.