Labor rate = $7.50 per hour Labor time = 6.5 hours Retail price of parts = $0 Total job cost = $82.00 Overhead rate?

+2
Answers (1)
  1. 21 March, 17:05
    0
    Total cost job=

    Retail price of parts+labor cost+manufacturing overhead

    Total cost job 82

    Retail price of parts 0

    Labor cost=7.5*6.5=48.75

    Manufacturing overhead?

    82=0+48.75+?

    ?=82-48.75

    ?=33.25

    Manufacturing overhead is 33.25

    Now find manufacturing overhead rate from the cost of labor

    33.25:48.75=0.682*100=68.2%

    The answer 68.2%