Miller Company operates 16 hours a day, 280 days a year. Employees work two 8 hour shifts. In an average month, 40 employees work 25 days and a total of 160 hours are missed. What is the rate of absenteeism?

+3
Answers (1)
  1. 13 July, 06:58
    0
    160 missed hrs / month / 40 employees

    = 4 hrs missed per month per employee
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Miller Company operates 16 hours a day, 280 days a year. Employees work two 8 hour shifts. In an average month, 40 employees work 25 days ...” in 📗 Advanced Placement (AP) if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.