Ask Question
4 August, 17:23

During the current year, Esterhazy, Inc. estimated manufacturing overhead for the year to be $896,000. The company uses direct labor hours to apply manufacturing overhead to Work-in-Process. The budgeted direct labor hours for the current year totaled 80,000 hours and the actual hours worked were 82,000. The actual overhead incurred during the year was $924,000. What is the amount of overapplied or underapplied overhead?

+3
Answers (1)
  1. 4 August, 17:37
    0
    Overheads are over-applied by $5,600

    Explanation:

    Company's expected manufacturing overhead = $896,000

    Budgeted labor hours = 80,000 hours

    Rate per hour = $896,000/80,000 = $11.2 per labor hour

    Actual overheads incurred = $924,000

    Actual labor hours = 82,000

    Actual rate per hour = $924,000/82,000 = $11.268

    Actual overheads at budgeted rate for actual hours = 82,000 X $11.2 = $918,400

    Since actual overheads are higher by $924,000 - $918,400 = $5,600

    Overheads are over-applied by $5,600
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “During the current year, Esterhazy, Inc. estimated manufacturing overhead for the year to be $896,000. The company uses direct labor hours ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers