A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start of the project), but activity C can only start after B is completed. The project ends when all activities are completed. The durations of the activities were simulated 10 times and the following values were obtained: Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?

+4
Answers (1)
  1. 27 May, 07:23
    0
    Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?

    Since B is the predecessor of C.

    Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B + Duration of C).

    Represent

    Run = R

    Duration of A = DA

    Duration of B = DB

    Duration of C = DC

    Project Completion time = PT

    R DA DB DC PT

    1 51 48 17 48 + 17 = 65

    2 60 48 19 48 + 19 = 67

    4 31 48 22 48 + 22 = 70

    5 30 31 14 31 + 14 = 45

    6 41 16 17 41

    7 44 12 6 44

    8 44 12 10 44

    9 45 43 9 43 + 9 = 52

    10 60 41 10 60

    Total = 546

    Total Project completion time in 10 Stimulations = 546

    Average project Completion time = 546/10 = 54.6

    Therefore, average Project completion time is between 53 and 56 days.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A project consists of three activities: A, B, and C. Activities A and B can begin at time 0 (start of the project), but activity C can only ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.