Ask Question
5 February, 05:51

A project has an original project budget of $1,150 and both the Cost Performance Index (CPI) and Schedule Performance Index (SPI) are equal to 1. Assuming the project will continue to spend money at the same rate, what is the estimate at completion (EAC) of the project

+1
Answers (2)
  1. 5 February, 06:10
    0
    Answer: The answer is $1,150

    Explanation:

    Using the formula EAC = BAC / CPI

    Where EAC = Estimate at completion, BAC = Budget at completion, CPI = Cost Performance Index,

    Since the project will continue to spend money at the same rate

    Since the original project budget is $1,150 then,

    EAC = 1,150 / 1

    = 1,150

    Therefore the estimate at completion is $1,150
  2. 5 February, 06:15
    0
    Answer: $1150

    Explanation:

    It is give that SPI and CPI is equal to 1, which means project will continue to spend at the same current rate. Therefore we can use following formula:

    EAC = BAC/CPI

    BAC = Budget at completion = $1150

    EAC = $1150 / 1 = $1150
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A project has an original project budget of $1,150 and both the Cost Performance Index (CPI) and Schedule Performance Index (SPI) are equal ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers