Swan, Inc. uses the high-low method to analyze cost behavior. The company observed that at 20,000 machine hours of activity, total maintenance costs averaged $37.30 per hour. When activity jumped to 25,000 machine hours, which was still within the relevant range, the average total cost per machine hour was $31.30.

+5
Answers (1)
  1. 17 April, 21:19
    0
    7.3

    Explanation:

    37.30 * 20,000 = $746,000

    31.30 * 25000 = $782,500

    $746,000-$782,500 = $36,500

    36,500 / 5,000 = 7.3

    Note:

    25,000-20 000 = 5,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Swan, Inc. uses the high-low method to analyze cost behavior. The company observed that at 20,000 machine hours of activity, total ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.