Shamrock manufacturing budgeted fixed overhead costs of? $2.75 per unit at an anticipated production level of? 1,350 units. in july shamrock incurred actual fixed overhead costs of? $4,400 and actually produced? 1,300 units. what is? shamrock's fixed overhead volume variance in? july?

+5
Answers (1)
  1. 28 February, 23:09
    0
    We are asked to solve for the fixed budget variance given the Shamrock Manufacturing has the following values:

    Total Production Units = 1,350

    Overhead Cost per Unit = $2.75

    Actual Fixed Overhead Cost = $4,400

    Solving for Fixed Budget Variance (FBV), we have:

    FBV = Actual Fixed Overhead Cost - Total Production*Overhead Cost per Unit

    FBV = $4,400 - (1350 * $2.75)

    FBV = $687.50

    The answer is $687.50.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Shamrock manufacturing budgeted fixed overhead costs of? $2.75 per unit at an anticipated production level of? 1,350 units. in july ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.