Ask Question
Today, 12:48

The Development Team has not completed any of the Product Backlog Items selected for the Sprint by Sprint end. Next step is A. Extend the Sprint since Scrum favors "getting done" B. Advice the Product Owner to accept the completed portion of the incomplete Product Backlog Items, and plan to complete them by next Sprint, since Scrum favors "empowered teams" C. End the Sprint with a Retrospective, since Scrum favors "time boxing"

+2
Answers (1)
  1. Today, 13:17
    0
    B. Advice the Product Owner to accept the completed portion of the incomplete Product Backlog Items, and plan to complete them by next Sprint, since Scrum favors "empowered teams"

    Explanation:

    If for instance, all the items of a Sprint are not completed, the Sprint is still marked over and the remaining item (s) is moved to the Product Backlog from where it can be scheduled to any of the subsequent sprint based on the revised priority. Similarly, the Sprint can never be shortened.

    the product owner is the person responsible for prioritizing the backlog. And the product owner should always be just one person. Definitely Product Owner. The only person that knows 100% what the needs of a company are and what's going to bring the most value is the Product Owner.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The Development Team has not completed any of the Product Backlog Items selected for the Sprint by Sprint end. Next step is A. Extend the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers