Rutch Corporation manufactured 54,000 door jambs during September. The fixed-overhead cost-allocation rate is $50.00 per machine-hour. The following fixed overhead data pertain to September: Actual Static Budget Production 54,000 units 60,000 units Machine-hours 985 hours 1,150 hours Fixed overhead costs for September $53,400 $57,500 What is the flexible-budget amount

+1
Answers (1)
  1. 27 December, 05:21
    0
    flexible-budget amount is $57,500

    Explanation:

    given data

    fixed-overhead cost-allocation rate = $50.00 per machine-hour

    Actual Static Budget

    Production 54,000 units 60,000 units

    Machine-hours 985 hours 1,150 hours

    Fixed overhead costs $53,400 $57,500

    for September

    solution

    we get here flexible-budget amount so as we know flexible-budget amount is here the same lump sum as the static budget

    so that

    flexible-budget amount September is $57,500
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Rutch Corporation manufactured 54,000 door jambs during September. The fixed-overhead cost-allocation rate is $50.00 per machine-hour. The ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.