Ask Question
3 October, 14:03

Churz Corporation's management reports that its average delivery cycle time is 31 days, its average throughput time is 12.0 days, its manufacturing cycle efficiency (MCE) is 0.40, its average move time is 0.5 day, and its average queue time is 5.0 days.

Required:

a. What is the wait time? (Round your answer to 1 decimal place.)

b. What is the process time? (Round your answer to 1 decimal place.)

c. What is the inspection time? (Round your intermediate calculations and final answer to 1 decimal place.)

+1
Answers (1)
  1. 3 October, 14:06
    0
    Check the explanation

    Explanation:

    Answer a.

    Delivery Cycle Time = 31.0 days

    Throughput Time = 12.0 days

    Delivery Cycle Time = Throughput Time + Wait Time

    31.0 = 12.0 + Wait Time

    Wait Time = 31.0 - 12.0

    Wait Time = 19.0 days

    Answer b.

    MCE = 0.40

    Throughput Time = 12.0 days

    MCE = Process Time / Throughput Time

    0.40 = Process Time / 12.0

    Process Time = 4.80 days

    Answer c.

    Throughput Time = Process Time + Inspection Time + Move Time + Queue Time

    12.0 = 4.80 + Inspection Time + 0.5 + 5.0

    12.0 = 10.3 + Inspection Time

    Inspection Time = 1.7 days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Churz Corporation's management reports that its average delivery cycle time is 31 days, its average throughput time is 12.0 days, its ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers