Which of the following statements concerning work packages is NOT correct? a. Work packages are activity elements with detailed descriptions of tasks and dependencies b. Work packages are the elements at the lowest level of the WBS. c. Work packages are the basis for subsequent project planning activities. d. Work packages are the basis for subsequent project control activities.

+2
Answers (1)
  1. 5 March, 15:21
    0
    d. Work packages are the basis for subsequent project control activities.

    Explanation:

    That is not true about work planning. Instead, it is the basis for subsequent project planning activities