A project's opportunity cost of capital is:

Multiple Choice:

O the return that shareholders could expect to earn by investing in the financial markets.

O the return earned by investing in the project.

O equal to the average return on all company projects.

O designed to be less than the project's IRR.

+1
Answers (1)
  1. 24 August, 22:03
    0
    the return that shareholders could expect to earn by investing in the financial markets

    Explanation:

    Projects are financed from a joined pool of funds. The Cost of Capital is the minimum return that a project must offer before it can be accepted and this is determined by the return that shareholders could expect to earn by investing in the financial markets.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A project's opportunity cost of capital is: Multiple Choice: O the return that shareholders could expect to earn by investing in the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers