During 2017, Sheridan Company expected Job No. 26 to cost $300000 of overhead, $500000 of materials, and $200000 in labor. Sheridan applied overhead based on direct labor cost. Actual production required an overhead cost of $260000, $510000 in materials used, and $150000 in labor. All of the goods were completed. What amount was transferred to Finished Goods?

+1
Answers (1)
  1. 19 July, 05:07
    0
    The $885,000 was transferred to Finished Goods

    Explanation:

    The computation of the transferred amount to finished good is shown below:

    = Material used + labor cost + overhead cost

    where,

    Overhead cost = (Expected overhead : estimated labor) * actual labor cost

    = ($300,000 : $200,000) * $150,000

    = 1.5 * $150,000

    = $225,000

    The other items values would remain the same

    Now put these values to the above formula

    So, the value would equal to

    = $510,000 + $150,000 + $225,000

    = $885,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “During 2017, Sheridan Company expected Job No. 26 to cost $300000 of overhead, $500000 of materials, and $200000 in labor. Sheridan applied ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.