jalbert incorporated planned to use materials of $11 per unit but actually used materials of $13 per unit, and planned to make 1590 units but actually made 1780 units. the flexible budget variance for materials is?

+2
Answers (1)
  1. 14 November, 14:17
    0
    Flexible budgeted variance is 3560 unfavorable

    Explanation:

    We have given budgeted cost to use the material = $11 per unit

    And actual cost to use the material = $12 per unit

    Budgeted unit produced = 1590 units

    And actual unit produced = 1780 units

    We have to find the flexible budgeted variance

    Flexible budgeted variance is given by

    Flexible budgeted variance = (Budgeted cost of material - Cost of material used) * actual units produced = ($11 - $13) * 1780 = - 3560 (unfavorable)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “jalbert incorporated planned to use materials of $11 per unit but actually used materials of $13 per unit, and planned to make 1590 units ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.