On January 2, 2020, Concord Corporation replaced its boiler with a more efficient one. The following information was available on that date: Purchase price of new boiler $140500 Carrying amount of old boiler 8500 Fair value of old boiler 3200 Installation cost of new boiler 21600 The old boiler was sold for $3200. What amount should Concord capitalize as the cost of the new boiler

+1
Answers (1)
  1. 17 January, 04:35
    0
    The amount that Concord should capitalize as the cost of the new boiler is $162,100

    Explanation:

    Solution

    Recall that:

    The price of purchasing a new boiler = $140500

    The amount of old boiler = 8500

    The cost of installation of new boiler = $21600

    Old boiler sold for = $3200

    Now,

    The Cost of New Boiler = Purchase Price of new boiler + Installation cost of new boiler

    = $140500 + 21600

    = $162,100
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “On January 2, 2020, Concord Corporation replaced its boiler with a more efficient one. The following information was available on that ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.