If one of the activities on the critical path is delayed, the entire project will be delayed.

b. the critical path is the sequence of activities between a project's start and finish that takes the shortest time to complete.

c. there may be more than one critical path in a project network.

d. the activities along the critical path determine the completion time of the project.

+5
Answers (1)
  1. 13 September, 23:31
    0
    Must be d all activities must be completed for project completion
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “If one of the activities on the critical path is delayed, the entire project will be delayed. b. the critical path is the sequence of ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.