A company has a process that results in 34000 pounds of Product A that can be sold for $8 per pound. An alternative would be to process Product A further at a cost of $227800 and then sell it for $14 per pound. Should management sell Product A now or should Product A be processed further and then sold? What is the effect of the action?

+1
Answers (1)
  1. 23 November, 23:32
    0
    After calculating, we get to know that the Product A should be sell now because, it show a difference of $23,800 through which company can earn more in the future. As the company will be better off by $23,800

    Explanation:

    For calculation, following things need to be considered which is shown below:

    1. Product A process costing = Pounds * Per pound price

    = 34,000 * $8

    = $272,000

    2. Product A costing after selling = Pounds * sale price per pound

    = 34,000 * $14

    = $476,000

    3. Difference of costing:

    = Product A costing after selling - Product A process costing

    = $476,000 - $272,000

    = $204,000

    4. Invested amount = $227,800

    5. Actual Difference = Invested amount - costing difference

    = $227,800 - $204,000

    = $23,800

    After calculating, we get to know that the Product A should be sell now because, it show a difference of $23,800 through which company can earn more in the future. As the company will be better off by $23,800
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A company has a process that results in 34000 pounds of Product A that can be sold for $8 per pound. An alternative would be to process ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.