A bottleneck happens when a key piece of manufacturing machinery can produce 1,000 units per hour and demand for the product supports a production rate of 1,200 units per hour.

a. True

b. False

+5
Answers (1)
  1. 10 August, 04:48
    0
    B. True ...
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A bottleneck happens when a key piece of manufacturing machinery can produce 1,000 units per hour and demand for the product supports a ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.