Jefferson Co. uses the following standard to produce a single unit of its product: variable overhead $7.40 (2 hrs. per unit @ $3.70/hr.). Actual data for the month show variable overhead costs of $189,480, and 24,700 units produced. The total variable overhead variance is:

+3
Answers (1)
  1. 11 December, 21:42
    0
    The total variable overhead variance is $6,700 unfavorable

    Explanation:

    The total variable overhead is a difference between budgeted overhead and actual overhead.

    In mathematically,

    Total variable overhead = Budgeted overhead - actual overhead

    where,

    Budgeted overhead = Variable cost unit produced * variable overhead

    = 24,700 * $7.40

    = $182,780

    And actual overhead is $189,480

    So,

    Total variable overhead = $182,780 - $189,480 = - $6,700 unfavorable

    Hence, The total variable overhead variance is $6,700 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Jefferson Co. uses the following standard to produce a single unit of its product: variable overhead $7.40 (2 hrs. per unit @ $3.70/hr.). ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.