Refer to the table below. what is the cumulative budgeted cost at the end of week 6? amounts are in thousands of dollars.

+3
Answers (1)
  1. 17 December, 22:07
    0
    The cumulative budgeted cost at the end of week 6 is $100,000. The answer in this question whose are amounts are in thousand of dollars is $100,000. So, the cumulative budgeted cost at the end of the week 6 is $100,000. Cumulative budgeted cost or acronym of CBC is the amount that is budgeted in order to accomplish the work that was scheduled.