Both Projects A and B are acceptable as independent projects. However, the selection of either one of these projects eliminates the option of selecting the other project. Which one of the following terms best describes the relationship between Project A and Project B?

(A) Dual return

(B) Conventional Crosswise

(C) Multiple choice

(D) Mutually exclusive

+4
Answers (1)
  1. 6 December, 20:39
    0
    (D) Mutually exclusive

    Explanation:

    Mutually exclusive means that both projects cannot be chosen at the same time. The selection of either one of the projects eliminates the option of selecting the other project.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Both Projects A and B are acceptable as independent projects. However, the selection of either one of these projects eliminates the option ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.