You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes and the sum of all that tasks required on the line is 25 minutes. Which of the following is the correct value for the resulting line's efficiency?

A. 0.500

B. 0.833

C. 0.973

D. 0.990

E. None of these

+4
Answers (1)
  1. 25 October, 09:12
    0
    option (B) 0.833

    Explanation:

    Data provided in the question:

    Actual number of workstations that will be used on an assembly line = 6

    Cycle time of the line = 5 minutes

    Sum of all that tasks required on the line = 25 minutes

    Now,

    Resulting line's Efficiency

    = [ Sum of all task times ] : [ Actual number of workstations * cycle time ]

    or

    Resulting line's Efficiency = 25 minutes : [6 * 5 minutes]

    = 0.833

    Hence,

    The answer is option (B) 0.833
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.