Ask Question
10 November, 09:12

Cycle time includes: Select one: a. Processing time, inspection time, and inventory time. b. Processing time, storage and waiting time, finishing time, and selling time. c. Processing time, storage and waiting time, movement time, and inspection time. d. Processing time, storage and waiting time, movement time, and finishing time.

+4
Answers (2)
  1. 10 November, 09:27
    0
    The correct answer is letter "C": Processing time, storage and waiting time, movement time, and inspection time.

    Explanation:

    Cycle times include all the times necessary for the manufacturing of a product. Cycle times consider in the calculation of the time the value-added time and non-value added time. The computation mainly implies the processing time, storage and waiting time, movement time, and inspection time which are the steps necessary for the assembly and quality control of the product before it is delivered to customers.
  2. 10 November, 09:38
    0
    ok i will
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Cycle time includes: Select one: a. Processing time, inspection time, and inventory time. b. Processing time, storage and waiting time, ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers