Ask Question
10 March, 16:58

Carlson Company uses a predetermined rate to apply overhead. At the beginning of the year, Carlson estimated its overhead costs at $240,000, direct labor hours at 40,000, and machine hours at 10,000. Actual overhead costs incurred were $249,280, actual direct labor hours were 41,000, and actual machine hours were 11,000. If the predetermined overhead rate is based on machine hours, what is the total plantwide applied overhead for the year?

+4
Answers (1)
  1. 10 March, 17:00
    0
    Allocated MOH = $264,000

    Explanation:

    Giving the following information:

    Estimates overhead costs = $240,000

    Estimated machine hours = $10,000.

    The actual machine hours were 11,000.

    To allocate overhead based on machine-hours, first, we need to calculate the estimated overhead rate:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 240,000/10,000 = $24 per machine-hour

    Now, we can allocate overhead:

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base

    Allocated MOH = 24*11,000 = $264,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Carlson Company uses a predetermined rate to apply overhead. At the beginning of the year, Carlson estimated its overhead costs at ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers