Gilchrist Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. At the beginning of the most recently completed year, the Corporation estimated the machine-hours for the upcoming year at 79,000 machine-hours. The estimated variable manufacturing overhead was $7.38 per machine-hour and the estimated total fixed manufacturing overhead was $2,347,090. The predetermined overhead rate for the recently completed year was closest to:

A) $37.09 per machine-hour

B) $36.07 per machine-hour

C) $7.38 per machine-hour

D) $29.71 per machine-hour

+4
Answers (1)
  1. 31 May, 08:01
    0
    The correct answer is A.

    Explanation:

    Giving the following information:

    The estimated machine-hours for the upcoming year at 79,000 machine-hours.

    The estimated variable manufacturing overhead was $7.38 per machine-hour

    The estimated total fixed manufacturing overhead was $2,347,090.

    To calculate the estimated manufacturing overhead rate we need to use the following formula:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 2,347,090/79,000 + 7.38 = $37.09 per machine-hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Gilchrist Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. At the beginning of the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.