Job 731 was recently completed. The following data have been recorded on its job cost sheet: Direct Materials: $2,500 Direct Labor hours: 100 Direct Labor wage rate: $10.00 per hour The company applies manufacturing overhead on the basis of direct labor cost. The pre-determined overhead rate is 150% of direct labor cost. The total cost that would be recorded on the job cost sheet for job 731 would be:

+5
Answers (1)
  1. 28 June, 17:35
    0
    Total cost = $5,000

    Explanation:

    Giving the following information:

    Job 731:

    Direct Materials = $2,500

    Direct Labor hours = 100

    Direct Labor wage rate: $10.00 per hour

    First, we need to calculate the direct labor cost and then allocate overhead:

    Direct labor = 100*10 = $1,000

    Allocated overhead = 1,000*1.5 = $1,500

    Total cost = 2,500 + 1,000 + 1,500

    Total cost = $5,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Job 731 was recently completed. The following data have been recorded on its job cost sheet: Direct Materials: $2,500 Direct Labor hours: ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.