Job 731 was recently completed. The following data have been recorded on its job cost sheet: Direct Materials: $2,500 Direct Labor hours: 100 Direct Labor wage rate: $10.00 per hour The company applies manufacturing overhead on the basis of direct labor cost. The pre-determined overhead rate is 150% of direct labor cost. The total cost that would be recorded on the job cost sheet for job 731 would be:
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Job 731 was recently completed. The following data have been recorded on its job cost sheet: Direct Materials: $2,500 Direct Labor hours: ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.