Ask Question
7 May, 07:51

The materials purchase price variance, in a standard cost system, is obtained by multiplying the: Group of answer choices a. Actual price by the difference between actual quantity purchased and standard quantity used. b. Actual quantity purchased by the difference between actual price and standard price. c. Standard price by the difference between standard quantity purchased and standard quantity used. d. Standard quantity purchased by the difference between actual price and standard price.

+4
Answers (1)
  1. 7 May, 08:05
    0
    b. Actual quantity purchased by the difference between actual price and standard price

    Explanation:

    The formula to compute the material purchase price is shown below:

    = Actual Quantity * (Standard Price - Actual Price)

    It is derived by taking a difference between the standard price and the actual price and then multiplying it by the actual quantity so that the material price or material purchase price variance could come

    Hence, the correct option is b.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The materials purchase price variance, in a standard cost system, is obtained by multiplying the: Group of answer choices a. Actual price ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers