Determine the total cost for this plan given the following forecast:
Month 1 2 3 4 5 6
Forecast 380 400 420 440 460 480
Use steady regular output of 400 unites per month, use overtime as needed for up to 40 unites per month, and use subcontracting to make up any needed output to match the forecast. Unit costs are:
Regular output = $25
Overtime = $40
Subcontract = $60
Average balance inventory = $15
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Determine the total cost for this plan given the following forecast: Month 1 2 3 4 5 6 Forecast 380 400 420 440 460 480 Use steady regular ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Home » Business » Determine the total cost for this plan given the following forecast: Month 1 2 3 4 5 6 Forecast 380 400 420 440 460 480 Use steady regular output of 400 unites per month, use overtime as needed for up to 40 unites per month, and use subcontracting