Ask Question
6 April, 05:43

During a Sprint, the features are broken down into smaller elements and put on theSprint Backlog. Which one of the following statements best describes these smallerelements?

a. Activities estimated in duration scrum

b. Tasks estimated in hours (effort)

c. Tasks estimated in duration

d. Activities estimated in hours (effort)

+5
Answers (1)
  1. 6 April, 05:45
    0
    The correct answer is letter "B": Tasks estimated in hours (effort).

    Explanation:

    Sprint Planning meeting is the first Scrum event where tasks are planned for the ongoing Sprint. In this Sprint, the Scrum master, product owner, and the development team participate to share ideas. The tasks are broken down into small duties that the development team members can select. Those tasks are estimated in hours, being the total amount of hours the total work.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “During a Sprint, the features are broken down into smaller elements and put on theSprint Backlog. Which one of the following statements ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers