JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $2,410,000. JRE2 recognizes revenue upon contract completion. Cost incurred Estimated Cost to Complete 2020 $ 278,000 $ 1,690,000 2021 1,740,000 654,000 2022 590,000 0 In 2022, JRE2 would report gross profit (loss) of:

+4
Answers (1)
  1. 8 November, 12:13
    0
    -$262,000

    Explanation:

    The calculation of gross profit or loss is shown below:-

    Total revenue = $2,410,000

    Total cost incurred = $278,000 + $1,740,000

    = $2,018,000

    Project total estimated cost = $2,018,000 + $654,000

    = $2,672,000

    Total income = Total revenue - Project total estimated cost

    = $2,410,000 - $2,672,000

    =-$262,000

    Therefore for computing the gross loss we simply deduct the project total estimated cost from total revenue.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $2,410,000. JRE2 recognizes revenue upon contract completion. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.