Except in rare circumstances, project teams should not attempt to decompose work packages into project activities because work packages provide sufficient detail to develop a project schedule.

a. True

b. False

+1
Answers (1)
  1. 12 October, 18:56
    0
    The statement is False

    Explanation:

    Work packages is the one which is described as the group of the tasks which are related within the project. As the work packages look like the projects themselves, and they are usually the sub - projects from the larger or big project.

    The statement is false as work packages does not provide the sufficient detail for developing the schedule of the project as the work packages are the smallest unit of the work and the group of the tasks related to the products.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Except in rare circumstances, project teams should not attempt to decompose work packages into project activities because work packages ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers