Selected accounts with amounts omitted are as follows: Work in Process Aug. 1 Balance 271,240 Aug. 31 Goods finished 190,490 31 Direct materials X 31 Direct labor 32,700 31 Factory overhead X Factory Overhead Aug. 1 - 31 Costs incurred 112,690 Aug. 1 Balance 12,130 31 Applied (30% of direct labor cost) X If the balance of Work in Process on August 31 is $209,910, what was the amount debited to Work in Process for direct materials in August?

+5
Answers (1)
  1. 12 August, 12:30
    0
    Debited Amount to WIP for Direct Materials in august is $629,130.

    Explanation:

    According to the scenario, computation of the given data are as follows:-

    Applied Factory Overhead = 30% of Direct Labor Cost

    = $32,700 * 30 : 100 = $9,810

    Total Manufacturing Cost = Finished Goods of WIP + Closing Balance of WIP - Opening Balance of WIP

    = $190,490 + $209,910 - $271,240 = $671,640

    Debited Amount to WIP for Direct Material = Total Manufacturing Cost - Direct Labor Cost - Applied Factory Overhead

    = $671,640 - $32,700 - $9,810

    = $629,130

    Debited Amount to WIP for Direct Materials in august is $629,130.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Selected accounts with amounts omitted are as follows: Work in Process Aug. 1 Balance 271,240 Aug. 31 Goods finished 190,490 31 Direct ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.