A production center is available for 8 hours per day in a factory. It is comprised of several rotary parts, and the worker operating it is required to lubricate these rotary parts once each day. It takes 2 hours to remove these parts from the equipment, lubricate them, and re-assemble them. The production center is not available for production during these times. The availability of the production center is:

+2
Answers (1)
  1. 7 November, 03:52
    0
    75%

    Explanation:

    Since the production center is available for 8 hours per day in a factory, and the worker operating it is required to lubricate these rotary parts once each day.

    If it takes 2 hours to remove these parts from the equipment, lubricate them, and re-assemble them and the production center is not available for production during these times;

    Then the availability of the production center is 75% which is derived by : [8 hours total - 2 hours downtime / 8 hours total availability] x 100 = 75%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A production center is available for 8 hours per day in a factory. It is comprised of several rotary parts, and the worker operating it is ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers