Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $3,100 of direct materials and used $4,600 of direct labor. The job was not finished by the end of the month, but needed an additional $3,600 of direct materials in October and additional direct labor of $7,100 to finish the job. The company applies overhead at the end of each month at a rate of 150% of the direct labor cost. What is the amount of job costs added to Work in Process Inventory during October?

a. $21,350.

b. $35,950.

c. $32,650.

d. $25,950.

e. $18,400.

+5
Answers (1)
  1. 9 February, 17:12
    0
    The answer is b.$35,950
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $3,100 of direct ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers