Mrp works best if the inventory items have dependent demand. True or false?

+5
Answers (1)
  1. Yesterday, 22:27
    0
    Answer: The correct answer is True.

    Explanation: Materials Requirement Planning works best if the inventory items have dependent demand. Dependent demand items are components of finished goods. For example, in a bicycle factory one of the inventory items may be tires.

    MRP is a system that works backwards, starting with a production plan for finished goods. This is used to develop requirements for components and raw materials needed to produce the final product within the established schedule.