Mary is managing a data migration project and the project is currently in the executing phase. The project's current total earned value (EV) is $25,000 and the current schedule variance (SV) is $5,000. What is the project's current schedule performance index (SPI) ?

+1
Answers (2)
  1. 30 September, 16:58
    0
    Answer:The answer is 1.25

    Explanation:

    To calculate SPI, we use the formula SPI = EV : PV

    EV = $25,000, PV = unknown, SV = $5,000

    SV = EV - PV

    5,000 = 25,000 - PV

    Making PV the subject of formula

    PV = 25,000 - 5,000

    PV = 20,000

    SPI = 25,000 : 20,000

    SPI = 1.25

    Since it is greater than 1, the project is on track and has a favourable conditions
  2. 30 September, 17:02
    0
    Schedule performance index (SPI) = 1.25

    Explanation:

    Earned value (EV) - planned value (PV) = Schedule variance (SV)

    25000 - PV = 5000

    collecting like terms means taking PV to the right-hand side of the equation & 5000 to the left-hand side of the equation.

    25000 - 5000 = PV

    PV = 20000

    Schedule performance index (SPI) = EV : PV

    SPI = 25000 : 20000 = 1.25
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Mary is managing a data migration project and the project is currently in the executing phase. The project's current total earned value ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.