A project manager is preparing two documents for risk management. One contains sources of overall project risk and also summary information on individual risks. The second describes individual risks identified. What name should the project manager give to the first document

+2
Answers (1)
  1. 1 January, 04:14
    0
    Answer: Risk Report

    Explanation:

    A Risk Report for a project contains all the risk that the project is exposed to. This includes both project risk as well as individual risks related to the components projects in the overall project.

    A Risk Report details the risks such as Supplier failure, Inflation, Pending Government Regulations and the like. It then takes these and summarizes them for presentation to those who require this information in the company so that appropriate safeguards may be set up and precautions taken.

    This describes the first document and so should be what the Project Manager names it.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A project manager is preparing two documents for risk management. One contains sources of overall project risk and also summary information ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.