Ask Question
16 November, 16:45

A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and schedule variances and CSI? Estimate the time variance.

+3
Answers (1)
  1. 16 November, 17:10
    0
    Answer and Explanation:

    Given:

    Actual time (AT) = 70 days

    Actual cost (AC) = $78,000

    Scheduled cost (SC) = $84,000

    Earned value (EV) = $81,000

    Computation of cost variance:

    Cost variance = Earned value - Actual cost

    Cost variance = $81,000 - $78,000

    Cost variance = $3,000

    Computation of schedule variance:

    Schedule variance = Earned value - Scheduled cost

    Schedule variance = $81,000 - $84,000

    Schedule variance = - $3,000

    Computation of Cost schedule Index (CSI):

    Cost schedule Index = EV² / (AC * SC)

    Cost schedule Index = ($81,000) ² / ($78,000 * $84,000)

    Cost schedule Index = 1.00137363

    Cost schedule Index = 1.001 (Approx)

    Computation of time variance:

    Time variance = (AT * CSI) - AT

    Time variance = (70 * 1.001) - 70

    Time variance = (70.07) - 70

    Time variance = 0.07 days
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers