The King Corporation manufactures custom-made furniture. The following data pertains to Job X4A:Direct materials placed into production $9,000Direct labor hours worked 300 hoursDirect labor rate per hour $ 15Machine hours worked 100 hoursPlantwide overhead rate is $22.50 per machine hour. Job X4A consists of 500 units. One-half of Job X4A was sold for $10,000. What is the cost per unit for Job X4A?

+2
Answers (1)
  1. 25 June, 10:55
    0
    Unitary cost of JobX4A = $31.5

    Explanation:

    Giving the following information:

    The following data pertains to Job X4A:

    Direct materials placed into production $9,000

    Direct labor hours worked 300 hours

    Direct labor rate per hour $ 15

    Machine hours worked 100 hours

    The plantwide overhead rate is $22.50 per machine hour.

    Job X4A consists of 500 units.

    One-half of Job X4A was sold for $10,000.

    Total cost of JobX4A = direct materials + direct labor + manufacturing overhead

    Total cost of JobX4A = 9000 + (300*15) + (100*22.5) = $15,750

    Unitary cost of JobX4A = 15750/500 = $31.5
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The King Corporation manufactures custom-made furniture. The following data pertains to Job X4A:Direct materials placed into production ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.